Emergency Shelter: Peter and Paul

These funds are being deployed to extend and expand contracts and leases with 4 emergency shelter providers (Magdala Foundation, Sister's Mission, Jefferson Spaces, and Mark Twain Hotel) formerly supported through FEMA and ESG-CV funds which were depleted in 2021. The city also established new contracts with Peter & Paul Community Services, Doorways, and City Hope St. Louis to reflect the city’s increased need for emergency shelter. These new contracts have allowed the city to expand the number of beds it supports from 380 to 470. Over $2M in funds have been spent to date.

Project Appropriation

Project Appropriation
$154,446.00

Total Programmed Funds

Total Programmed Funds
$154,446.00
100.0% programmed of total appropriation

Total Expenditures

Total Expenditures
$154,446.00
100.0% expended of total appropriation

Project Expenditures

Project Expenditures
Date Account Vendor Amount
04/19/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $2,917.72
04/19/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $4,453.15
05/10/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $4,486.44
06/02/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $6,198.89
07/07/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $5,528.77
08/31/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $12,834.94
09/12/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $11,513.46
10/06/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $10,967.79
11/08/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $10,422.27
12/12/2022 566000 PETER & PAUL COMMUNITY SERVICES, INC. $12,592.00
01/10/2023 566000 PETER & PAUL COMMUNITY SERVICES, INC. $15,625.21
02/10/2023 566000 PETER & PAUL COMMUNITY SERVICES, INC. $10,795.87
04/10/2023 566000 PETER & PAUL COMMUNITY SERVICES, INC. $11,750.68
05/10/2023 566000 PETER & PAUL COMMUNITY SERVICES, INC. $12,198.54
05/15/2023 566000 PETER & PAUL COMMUNITY SERVICES, INC. $12,360.50
06/07/2023 566000 PETER & PAUL COMMUNITY SERVICES, INC. $9,799.77

Definitions

  • Appropriated Funds: Total amount of authorized funding set aside for a specific purpose
  • Programmed Funds: Estimate and Apportionment (E&A) approved contracts, personnel services, Board Bill approved Intergovernmental agreements (IGA)
  • Expenditures: Total amount spent by departments

Notes and Contact

ARPA(SLFRF and ERA) reporting will be updated on a rolling monthly basis.

The Project and Expenditure data reported is through Sep 30, 2024.

The data was last updated on Nov 15, 2024.

ARPA - American Rescue Plan Act ($510,518,052.20)
SLFRF - Coronavirus State and Local Fiscal Recovery Funds ($498,076,054.00)
ERA - Emergency Rental Assistance ($12,441,998.20)

Please contact STLARPA@stlouis-mo.gov if you have questions about the data.

See Also

An overview of ARPA data can also be found on the ARPA Transparency Portal

Was this page helpful?      